Kosova e Re 500MW power plant

15/5/2019
Project development

€ 1.5 billion

$ 1.675 billion

Announced

15/5/2019


Overview:

  • Kosovo e Re is a 500MW coal fired power plant to be built in Prishtina, Kosovo.
  • In 2017, Kosovo awarded the development contract to UK listed power generation company ContourGlobal.
  • In 2019, General Electric companies was selected as the preferred bidder for the EPC and maintenance contract.
  • The project will be financed through 30% equity and 70% debt.
  • Under the concession agreement, ContourGlobal will undertake the project on a build-own-operate-transfer (BOOT) basis and transfer the ownership of the plant to the Government of Kosovo after 20 years of operation.

Rajeeb Gurung - Researcher

Jurisdiction:

Kosovo

Deal type:

Project development

Practice area:

Project development

Governing law:

New York

Industry sector:

Energy


Firms:

Party: ContourGlobal (Project developer)


Party: ContourGlobal (Project developer)